Location:
2929 Research Parkway
College Station, Texas 77845
Issued for Bid: February, 10 2017
Bids Due: February, 24 2017
Substantial Completion: June 2018
Contract Type: CMAR
General Project Scope
Total Square Footage: 138,892 SF
Est Construction Budget: $50MM
DIV 03 – CONCRETE
Deep Foundations 8,000 LF
Perimeter Foundation Walls 1,159.51 LF
Basement Walls 8,935.92 SF
CIP Walls 3,555.56 CY
Concrete ‐ Structure 16,000 CY
Parking Lots / Walks 70,000 SF
Precast Concrete Cladding 2,000 SF
DIV 04 – MASONRY
Concrete Masonry Units 8,000 SF
Face Brick 28,000 SF
DIV 05 – METALS
Structural Steel 350 TN
DIV 06 – WOODS, PLASTICS & COMPOSITES
Laboratory Casework 800 LF
Standard Casework 1,500 LF
DIV 07 – THERMAL AND MOISTURE
Built Up Roofing 70,000 SF
DIV 08 – OPENINGS
Curtainwall 8,000 SF
Storefront 4,000 SF
DIV 09 – FINISHES
Ceramic Tile 10,000 SF
Carpet 800 SY
Vinyl Composition Tile
DIV 10 – SPECIALTIES
Laboratory Specialties
DIV 11 – EQUIPMENT
Security Equipment
AV Equipment
DIV 12 – FURNISHING
TBD
DIV 13 – SPECIAL CONSTRUCTION
Lightning Protection
DIV 14 – CONVEYING EQUIPMENT
Traction Elevator ‐ Passenger 4 EA
Traction Elevator ‐ Freight 1 EA
50 ton Overhead Cranes 2 EA
20 ton Overhead Cranes 1 EA
DIV 21 – FIRE SUPPRESSION
DIV 22 – PLUMBING
DIV 23 – HVAC
DIV 26 – ELECTRICAL
DIV 27 – COMMUNICATIONS
DIV 31 – EARTHWORK
DIV 32 – EXTERIOR IMPROVEMENTS